Let’s recap where we have been the past 6 weeks:
- Completed all interior walls of the basement; including the stairs to the main floor. We had a minor “change order” for the stairs—instead of walking into the mechanical room and then making a hard 180 degree turn to the upstairs, we added length to the stairs and shortened the height of the landing deck in the basement. This resulted in less stair treads in the basement and allowed us to have dual exits—to the mechanical room and the garage. We had to give up the linen closet in the hallway and move it into the second bathroom—we’re ok with this.
- Main floor had lots of framing:
- All exterior walls and windows
- All interior walls, including kitchen, great room, hallway, Den, bathroom 2, master bedroom, master bath, master dressing room, laundry room, pantry, north and east entrance (read; lots of 2x4’s!)
Interior basement stairs
Main floor (looks small)
Big blue working on the first wall in the master bathroom
Rear(east) walls
From the vineyard
Mainfloor Panorama
19”x 5 ½" x 24’ beam – biggest in the house
Supervisor and Troublemaker